Special General/Finance Committee

Public Input on 2024 Budget

A Special General/Finance Committee meeting was held to obtain public input into the 2024 budget.  Chair Mazan explained that there was no staff report for the meeting as Committee was present to listen to public input on the 2024 budget.

Delegations spoke regarding:

  • a one-time funding request from the Muskoka Watershed Council to help establish an integrated watershed management plan,
  • that sufficient monies should be made available for prudent service level enhancements in by-law enforcement, septic inspections, building inspectors and planning issues,
  • does the 10 Year Forecast include deferred work,
  • increasing the use of the arenas to six days a week for pickleball and adding a sixth pickleball court, and
  • the economic impact that the Muskoka Lakes Chamber of Commerce has across the entire Township of Muskoka Lakes.

The Board of the Muskoka Ratepayers submitted comments in writing to Committee and staff – Click Here.  Mayor Kelley reference the MRA’s submission stating that it provided helpful guidance and recommended that all members read it.

As this meeting was to obtain public input no resolution was read.

Thursday, September 7th, 2023

General/Finance Committee

Muskoka Lakes Museum 2023 Activity Update

Liz Lundell, Board Chair of the Muskoka Lakes Museum reviewed the history of the museum and the museum’s activities in 2023. The Muskoka Lakes Museum was founded in 1964 by volunteers and run as an independent co-operation. The museum maintains a 5300 square foot facility with 4500 artifacts on display. As of August 26th, 2023, the Museum had seen 1406 visitors, 72% of whom were visiting the area while 28% were either seasonal or full-time residents.

During the summer months the Museum hosted an After Hours Lecture Series, a children’s program of crafts and games, took part in Walker’s Point Pioneer Days with a demonstration on butter churning, and hosted a Picnic In The Past. This season the Museum featured a new and expanded “resort room” displaying a guest registry from Pinelands Resort from the early 1900’s and a display on early toys.

Ms. Lundell finished her delegation by stating that the Museum has submitted a grant request in the 2024 budget and stated that Township funding is critical to their operations.

This item was for information and no resolution was read.

Wednesday, September 13th, 2023

Arena Feasibility Study Update

Susan Lennox from Lennox Architects Limited was before Committee to provide an update on the arena feasibility study – Click Here. Ms. Lennox explained that the “Site & Building Analysis Review” was completed, including visits to both arenas to inspect their conditions regarding architecture, civil engineering, structural engineering, mechanical engineering, refrigeration, and electrical engineering. Recommended repairs were divided into four categories: High Priority: requiring repair ASAP, Medium Priority: requiring repair in next few years, Low Priority: item at the end of their life and NA as item was in good working order. As outlined in the report repairs are required at both facilities.

Ms. Lennox explained that the next steps will be a “Community Needs Review” which will take place via a survey and then in person. It is anticipated that the in-person meetings will be with smaller groups to allow everyone a chance to speak.

This item was for information and no resolution was read.

2024 Budget Guidelines

Director of Financial Services, Mark Donaldson, informed Committee that staff were asking to be able to prepare a 2024 budget with a levy increase of 6.9% over the approved 2023 levy. Mr. Donaldson explained that of the 6.9% increase 3.7% is net operating costs, with the remaining 3.2% contributions to reserves. Mr. Donaldson further explained that the 6.9% increase will allow the Township to provide the same services they did in 2023 but at 2024 prices but does not include any new spending, and that the Township cannot remain “status quo” with contribution to reserves as it is not sustainable.

During discussion Councillor Zavitz suggested that the seven Master Plans, including the Community Improvement Project should have an amount of $500,000.00 designated towards their uses. Mayor Kelley stated that he felt the Township has “lost the thread” with all the separate “Master Plans” and nothing further should be added until the Township confirms they have a “clear strategy” moving forward. When asked how to find reductions in the 6.9% levy increase Councillor Nishikawa was told, that information will be provided at the next budget meeting.

A resolution was read and carried to allow staff to prepare a 2024 Draft Budget with a maximum increase of 6.9% over the approved 2023 levy.

New Staff Member Welcomed

During the meeting Chair Mazan took a moment to introduce James Cox the Township’s new Economic Development Officer. Mr. Cox has a long history in Economic Development, most recently the Economic Development Officer for the West Parry Sound Regional Economic Development Office and also brings experience from Goderich and Leamington.

ED Note: The Board of the MRA welcome Mr. Cox to his new position at the Township and as a member of the Muskoka community.

Council

Appeal to Order to Remedy

As reported in the August Township Watch an Order to Remedy was laid on a property in Port Carling for removing trees and building a gravel path along the shoreline which undermined tree roots. This item was discussed at the August Council meeting but was deferred to allow Chief Municipal By-Law Enforcement Officer, Rob Kennedy, the opportunity to speak to the appellants regarding a submission they made. Following that meeting Mr. Kennedy spoke to the appellants who said that the trees had been cut down by Hydro One, but to date no proof of such had been received.

Mr. Kennedy reviewed for Council that when by-law enforcement attended the property for a property standards complaint that they noticed multiple trees had been cut down all within 200 feet of the shoreline and that a pathway had been constructed along the Indian River where new gravel had been laid. During the construction of the pathway tree roots had been undermined and tree branches had been limbed.

The appellant spoke to Council stating that she was a nature lover, loved trees and would never remove a tree without a good reason. The appellant discussed the site alteration issue stating that a path already existed at the shoreline and no trees were taken down for it, that there had been no “altering of grade”, no blasting, no fill added or removed, and that the walkway is exempt from the by-law as it is less than six feet wide. When asked by Councillor Nishikawa if she had laid the gravel, the appellant said she had. The appellant further stated that they had not removed any trees outside of regular maintenance but following a “huge storm on December 23rd” that brought down trees, Hydro One had accessed the property to remove the trees.

Director of Developmental Services and Environmental Sustainability, David Pink reminded Council that the charges were before the Provincial Courts, but property owners have a right to appeal an Order to Remedy and that was before Council to confirm or withdraw. Mayor Kelley raised that the Order to Remedy included a remediation plan but one had not been received by the Township yet, to which the appellant said that with the appeal that timeline was extended.

A resolution to confirm the Order to Remedy was read. The appellant questioned why the resolution was written before Council even spoke to her. She stated that her appearance before them had been in vain as the Township “put an order on me” with no evidence. The resolution carried.

ED Note: This report is a reminder to check before you do any site alteration or tree removal within 200 feet of the shoreline.

Wednesday, September 13th, 2023

Medora Street Retaining Wall

Director of Public Works, Ken Becking informed Council that a bid had been received from Bronte Construction to complete the necessary work on the retaining wall on Medora Street in Port Carling. Director Becking acknowledged to Council that the quote was over the budgeted amount but said there would be savings if the project was deferred until March 2024. Although there was initial movement in the wall it has been stable since then, but Director Becking stated “that could change and change rapidly”. Director Becking explained that if the contract was approved and signed, and if changes in the wall did occur Bronte Construction would be contractually bound to respond.

Director Becking was asked by Councillor Bosomworth what the risks were to not commence the project, to which Director Becking explained that the wall could become destabilized. Councillor Moyer Kent questioned why only one bid was received for the project and Director Becking explained that there are not a lot of contractors in the area who do work of this type, that the project is being tendered later in the year, that the Township is seeing the effects of the labour shortage and that in his experience retaining walls are expensive.

A resolution was read to award the contract to Bronte Construction, to extend the design contract with Tatham Engineering with an increased amount, to increase the Capital Budget to cover the costs of the repairs and to allow Director Becking to execute the documents. The resolution carried.

ED Note: The MRA reported in the August Township Watch that the speed limit would be reduced to 40 KM in the vicinity of the retaining wall.  According to a report given at the District Engineering and Public Works Committee meeting this will no longer take place until the work begins in the area.

Planning Committee

Official Plan – Approval Authority Proposed Modifications

As reported in the August Township Watch the District of Muskoka is the approval body for the Township’s Official Plan (OP) which was adopted by the Township on October 12th, 2022. As the approval body, the District returned the OP to the Township with proposed modifications, which were deferred at the August Planning Committee meeting. At the meeting in September Chair Bosomworth suggested that the two main sections to be reviewed and commented on were Commercial Resorts and Mineral Aggregate Operations. Consultant, Nick McDonald walked Committee through the changes that he and Director of Development Services and Environmental Sustainability, David Pink, were suggesting. Both Mr. McDonald and Mr. Pink expressed that there was no intention to alter policy directions that had been put forth, but to provide clarity on issues.

The Official Plan and staff comments can be seen here: Staff Comments, District Comments following the August Planning Committee meeting, and the Township of Muskoka Lakes Official Plan.

Mr. McDonald reviewed changes section by section and explained why they had been made. Delegations were heard expressing concerns including but not limited to:

  • a good reason should be demonstrated when wording is changed,
  • the OP effects all who live and do business in the Township and should be reflective of all people,
  • that “single ownership of resorts” is acceptable, and
  • that the cumulative effect of word changes is very important.

Committee discussed changes that were made to wording in the OP and Mr. McDonald explained why one word was more effective than another. Including explaining that the OP must be defensible at the Ontario Land Tribunal if it is appealed.

Committee then heard from delegates regarding the aggregate policies with comments including, but not limited to:

  • that although groups had worked with District staff on wording regarding aggregate, they still believed stronger wording could be used,
  • that ambiguous wording such as “shall not be supported” and “strongly discouraged” should be changed to “shall not be permitted” and “shall be limited to”,
  • that mineral aggregate operations should be greater than 2 KM from waterfront areas and located no more than 10 KM from a Provincial Highway,
  • that wording such as “close proximity” is too open ended,
  • that clearer wording needs to be added regarding aggregate uses, and
  • that the small particulates from aggregate can travel for miles and get into the human respiratory system and can have a permanent impact on our lungs.

District planners stated that they understood the concerns being raised but explained that they are “scoped by legislation” and as Professional Planners their hands are tied. It was expressed that if changes were made to the aggregate portion of the OP and it was challenged that the Township may not have a strong footing.

Committee members discussed how the wording in the previous OP had been sufficient and questioned why it could not be moved forward and used in the adopted OP. Mr. McDonald reminded Committee that the District was saying they had a problem with the wording, and they are the approval authority. Mr. McDonald further stated that regardless of what the OP says if a citizen comes forward with an application for aggregate use the governing body, which in this case is the MNRF, would look at local policies but if they felt the local policies were not consistent with the Provincial Policy Statement that they would simply ignore local policies. Prior to the resolution being read Mr. Pink confirmed with Committee that they wished the following to be used regarding mineral aggregate operations in the OP:

  • that the language in the previous OP be retained,
  • that a 2 KM prohibition to waterfront areas be placed on mineral aggregate operations with reasons why this was put in place, and
  • include language regarding aggregate uses be within 10 KM of a Provincial Highway.

A resolution was read to inform the District of Muskoka that the Township of Muskoka Lakes Council “has no objections to the proposed modifications, as amended in Appendix “I” to Report PLAN-2023-145, to the adopted Township Official Plan, together with the further modifications as directed at the September 14th, 2023, Planning Committee meeting. And that the Township of Muskoka Lakes Council respectfully requests that the District of Muskoka Council expedite the approval of the Township’s Official Plan as modified (attached as Appendix “III” to Report PLAN-2023-145 and as directed at the September 14th, 2023, Planning Committee meeting).”. The resolution carried.

Thursday, September 14th, 2023

According to MPAC the Province of Ontario
has postponed Province wide property reassessments through 2021-2024.
Property taxes will continue to be based on your 2016 assessment.

This and more information can be found in
MPAC’s In Touch Newsletter – Click Here.